Q14. A and B finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How long will A alone take?
Concept: Work and Time Efficiency
Question
Q14. A and B finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How long will A alone take?
(A) 24 days (B) 30 days (C) 36 days (D) 40 days
(A) 24 days (B) 30 days (C) 36 days (D) 40 days
Try it yourself first
Hint: Pehle, har pair ka 1-din ka kaam nikal lo. Jaise, A aur B ka 1 din ka kaam hoga. Ab, in sab rates ko add karke dekho kya milta hai.
Step-by-step solution
- 1
Given Rates
A and B: work/day; B and C: work/day; C and A: work/day. - 2
Work Rate Principle
If a person takes days, their 1-day work is . - 3
Sum All Rates
Add all given 1-day work rates to find 's rate. - 4
Calculate Combined Rate
- 5
Simplify Sum
work/day. - 6
Find $(A+B+C)$'s Rate
work/day. - 7
Find A's Rate
- 8
Calculate A's Rate
work/day. - 9
Time for A Alone
Time taken by A alone days.
Final answer
(b) 30 days
Remember: Individual work rate = (Combined rate) - (Other's rate).
Was this solution helpful?
Quick check · test yourself
Agar P, Q aur R ek kaam ko milkar 6 din mein karte hain, aur P aur Q usi kaam ko 10 din mein karte hain, toh R akela woh kaam kitne din mein karega?
Ask the AI teacher about this question
Stuck on a step? Ask in your own words — English or Hinglish both work.
Sign in free to askMore Mathematics questions
- Multiple Concepts5. tan^-1x का x के सापेक्ष अवकलन है ................. [x, 11+x^2,1] 6. 6 वस्तुओं में से 3…
- Logarithm basicsExplain loga a clearly: what it is, why/how it happens, the key formula or law with a…
- 2. Attempt any EIGHT parts: (i) Simplify by justifying each step (ii) Factorize: a²+4b²…
- RelationsLet S = 1, 2, 3, ......, 10. Suppose M is the set of all the subsets of S, then the…
- Probability(घ) सिद्ध कीजिए कि यदि E और F स्वतन्त्र घटनाएँ हैं, तो E और F' भी स्वतन्त्र होंगी। 5. सभी…
- CalculusQue- find the area enclosed by y = x and y=x² dal find the intersections: x=x²⇒ x(x-1)=0…